Accepted
Accepted 31 Jul 2026 — job J-26-0315
Ironbark Fitout Group · Project pricing · 30 days EOM
Lines16 units · 2 lines
| Code | Product | Finish | Qty | Unit | Total | Margin | |
|---|---|---|---|---|---|---|---|
| KM-CRD-BS | The Credenza Base | Monument Matt | 6 | $440.00 | $2,640.00 | 50% | |
| KM-TRP-TF | Trapezium Table Frame | Monument Matt | 10 | $470.00 | $4,700.00 | 50% | |
Margin
- Sell (ex GST)
- $7,340
- Material
- $1,314
- Labour
- $2,366 · 32.9 h
- Standard cost
- $3,680
- Margin
- $3,660 · 50%
■ material■ labour■ margin
Standard cost is the BOM at today's material prices plus routing minutes at $72/h. Lead time 20 working days from acceptance.
KM Tubular Industries Pty Ltd
403 Grieve Parade, Altona North VIC 3025 · (03) 9369 9808 · web@kmtubular.com.au
ABN 72 661 249 270
Quotation
Q-26-0345
Date 22 Jul 2026
Valid until 21 Aug 2026
Prepared by David Vesely
Prepared for
Ironbark Fitout Group
Attn: Greg Ashby
greg@ironbarkfitout.com.au
41 Bertie Street, Port Melbourne, VIC
ABN 36 611 905 228
Accepted
| Item | Finish | Qty | Unit | Amount |
|---|---|---|---|---|
| KM-CRD-BS The Credenza Base | Monument Matt | 6 | $440.00 | $2,640.00 |
| KM-TRP-TF Trapezium Table Frame | Monument Matt | 10 | $470.00 | $4,700.00 |
| Subtotal (ex GST) | $7,340.00 |
| GST 10% | $734.00 |
| Total (inc GST) | $8,074.00 |
Project: Docklands office — Credenza & Trapezium
Finish: Monument Matt powder coat unless noted. Delivery: Delivered metro Melbourne, inside ground floor.
Lead time: approx. 20 working days from acceptance and receipt of deposit. Terms: 30 days EOM.
Designed & manufactured in Melbourne since 1969