KM Tubular

J-26-4836 · Gold Coast Hospitality Furniture

Client order — Richmond office
MYOB · synced 08:52 Demo 23 Oct 2026
In production
0 of 1 work orders built · due 28 Oct 2026
Gold Coast Hospitality Furniture · Ahmed Chen · PO GOL-77545 · from Q-26-7273 · Monument Matt
Production floor
Job value (ex GST)
$1,784
$0 invoiced · $1,784 to bill
On the floor
0%
Due
28 Oct
started 9 Oct
Forecast margin
47%
quoted at 47%
Work orders1 batches · 6.3 h estimated
WOProductQtyStationWhoEstActual
WO-26-32063 KM-CON-TB Cone Table Base
Monument Matt
4 Assembly & Upholstery Dom 6.3 h 4.7 h
Material reserved from the BOMs · $494
MaterialNeedsIssuedOn handAll jobsOn orderFreeStatusSupplier
D450 Disc 450 × 6 mm, laser cut 4 ea 0 141 97 0 44 OK Westside Laser & Fold
TP250 Top plate 250 × 250 × 5 mm, 4 holes 4 ea 0 529 429 0 100 OK Westside Laser & Fold
FIX-PK Fixing pack — table base 4 ea 0 997 607 0 390 OK Häfele Australia
LAM-WRP Laminate wrap sheet 3000 × 1300 (cones & drums) 1 sheet 0 18 7.25 0 10.75 OK Laminex
BUB-R Bubble wrap 1500 mm (per m) 12 m 0 2,017 1,267 0 750 OK Visy Packaging
CTN-L Carton — frame / chair 1200 × 800 × 600 4 ea 0 673 523 0 150 OK Visy Packaging
PC-MON Powder — Monument Matt 1.6 kg 0 84 81.75 0 2.25 OK Dulux Powder & Industrial Coatings
SH16 Mild steel sheet 2400 × 1200 × 1.6 1.2 sheet 0 48 34.78 0 13.22 OK Orrcon Steel
Conversation — Q-26-7273 → J-26-4836 · 4 Outlook
↓ RE: Quotation Q-26-7273 — Client order — Richmond office Ahmed Chen → Trevor Sonnenberg · Q-26-7273 · J-26-4836 08 Oct 2026 · 12:15
Hi Trevor, All good — please go ahead with Q-26-7273. Our PO is GOL-77545. Heights to be 720 mm finished, same as last order. Thanks, Ahmed
⛓ Quote number in subject
↑ Order confirmation J-26-4836 (your PO GOL-77545) Trevor Sonnenberg → Ahmed Chen · Q-26-7273 · J-26-4836 08 Oct 2026 · 10:12
Hi Ahmed, Thanks for the order. It's booked in as job J-26-4836 against quote Q-26-7273, due 2026-10-28. Kind regards, Trevor
⛓ Sent from KM Tubular
↑ Quotation Q-26-7273 — Client order — Richmond office Trevor Sonnenberg → Ahmed Chen · Q-26-7273 06 Oct 2026 · 08:49
Hi Ahmed, Thanks for the enquiry. Please find attached quotation Q-26-7273 for Client order — Richmond office — $1,784 ex GST, valid 30 days. Lead time is around 10 working days from order. You can accept online from the link in the quote. Kind regards, Trevor Sonnenberg KM Tubular Industries
⛓ Sent from KM Tubular
↓ Quote request — Client order — Richmond office Ahmed Chen → Trevor Sonnenberg · Q-26-7273 05 Oct 2026 · 13:44
Hi Trevor, Could you please quote the following for Client order — Richmond office: - 4 × Cone Table Base, Monument Matt Freight to Burleigh Heads please. Thanks, Ahmed Chen Account Manager | Gold Coast Hospitality Furniture (07) 5531 8830
⛓ Sender matched to contact
Linesadding a line raises its work orders and reserves its material
CodeProductFinishQtyUnitTotal
KM-CON-TB Cone Table Base Monument Matt 4 $446.00 $1,784.00
Job costing
Value
$1,784
Quoted cost
$942 · 47% margin
Material
$491
Labour
$451 · 6.3 h
Forecast cost
$942
Margin
$842 · 47%
Shop hours
6.3 h est · 4.7 h so far
Invoices$0 of $1,784
No invoices yet.
Purchase ordersBoard →
Nothing ordered against this job.
Delivery
Docket is created when the last batch passes QC.
11 Ern Harley Drive, Burleigh Heads QLD
Notes
Heights to be 720 mm finished, same as last order.