Invoiced
Done and invoiced
Adelaide Contract Furniture · Chris Tran · PO ADE-14236 · from Q-26-7179 · Black Satin
Job value (ex GST)
$2,520
$2,520 invoiced · $0 to bill
On the floor
100%
Due
16 Oct
started 30 Sep
Forecast margin
41%
quoted at 43%
Work orders2 batches · 10.7 h estimated
| WO | Product | Qty | Station | Who | Est | Actual | |
|---|---|---|---|---|---|---|---|
| WO-26-31892 KM-B26-9189 | KM-STU-CT Stuart Coffee Table Black Satin | 2 | Complete | Sio | 2.6 h | 2.8 h | |
| WO-26-31893 KM-B26-9190 | KM-CRD-BS The Credenza Base Black Satin | 4 | Complete | Sio | 8.1 h | 8.8 h |
Material reserved from the BOMs · $656
| Material | Needs | Issued | On hand | All jobs | On order | Free | Status | Supplier |
|---|---|---|---|---|---|---|---|---|
| FIX-PK Fixing pack — table base | 0 ea | 4 | 997 | 607 | 0 | 390 | Issued | Häfele Australia |
| GL-FELT Felt-base glide insert 25.4 | 0 ea | 32 | 1,866 | 1,086 | 0 | 780 | Issued | Richmond Wheel & Castor Co |
| GLS-10 Toughened glass top 10 mm, cut to size | 0 ea | 2 | 10 | 4 | 0 | 6 | Issued | Laminex |
| BUB-R Bubble wrap 1500 mm (per m) | 0 m | 24 | 2,017 | 1,267 | 0 | 750 | Issued | Visy Packaging |
| CTN-L Carton — frame / chair 1200 × 800 × 600 | 0 ea | 6 | 673 | 523 | 0 | 150 | Issued | Visy Packaging |
| PC-BLK Powder — Black Satin | 0 kg | 3.1 | 295 | 194.5 | 0 | 100.5 | Issued | Dulux Powder & Industrial Coatings |
| SS25 304 stainless SHS 25 × 25 × 1.2 | 0 m | 4.8 | 99 | 49.8 | 0 | 49.2 | Issued | Atlas Steels |
| S25 SHS 25 × 25 × 1.6 | 0 m | 27.2 | 521 | 264.4 | 0 | 256.6 | Issued | Orrcon Steel |
| T254 Round tube 25.4 × 1.6 ERW | 0 m | 7.6 | 920 | 871.8 | 0 | 48.2 | Issued | Orrcon Steel |
Conversation — Q-26-7179 → J-26-4770 · 0 Outlook
No emails on this job yet.
Linesadding a line raises its work orders and reserves its material
| Code | Product | Finish | Qty | Unit | Total | |
|---|---|---|---|---|---|---|
| KM-STU-CT | Stuart Coffee Table | Black Satin | 2 | $468.00 | $936.00 | |
| KM-CRD-BS | The Credenza Base | Black Satin | 4 | $396.00 | $1,584.00 | |
Job costing
- Value
- $2,520
- Quoted cost
- $1,429 · 43% margin
- Material
- $656
- Labour
- $828 · 11.5 h
- Forecast cost
- $1,484
- Margin
- $1,036 · 41%
- Shop hours
- 10.7 h est · 11.5 h so far
Running over the quoted cost — check the actual minutes on the work orders.
Invoices$2,520 of $2,520
INV-18908 SentIndent order — St Kilda fitout
$2,520 Purchase ordersBoard →
Nothing ordered against this job.
Delivery
DN-26-2768 Collected / deliveredRegional — Followmont · 15 Oct 2026 · signed Chris
30 Port Road, Hindmarsh SA